Your argument is valid but that depends of the Type of Project.
In a wider complex Project, a Labor resource will be never be assigned any partial hours or days to a certain activity.
Assignment of Partial Labor hrs or days to an activity is what I believe to be applicable only on a very simple Project with not more than 10 Activities.
Member for
24 years 9 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Fri, 2015-09-04 12:29
If a resource is used on several activities in parallel adjusting resource calendars is poor solution. Besides do you pian to change resource calendars with each schedule update?
Max Unit / Time is used for Resource Leveling Purposes.
THis means, in case you assigned a labor to work in a day more than Maximum Hours per day then it will show you Over allocated Resources. And when Levelling of Resources is applied then it will expand the Duration.
In your case, a separate Calendar for the Labor specifying the Working Hours is needed.
How is resource loading done using the resource tab?
In the Primavera P6 Professional User's Guide 2011 it has an example for determining resource availibility. This is what it says and based on what I'm trying to do:
'' Example: Determining resource availibility
If the selected resource is one person, a resonable value may be 8 hours (units) per day (duration). In this case, the Max Units / Time would be 8.00h/d, or 8 hours of work per day. Similarly, if the selected resource is a department with 5 people, then the Max Units/Time may be 40.00h/d. This means that 5 people can perform 40 hours of work per day, rather than 1 person performing 8 hours of work per day.''
Instead of increasing the hours per day, I want to decrease it. This feature is'nt working and I don't know why
Member for
15 years 9 months
Member for15 years9 months
Submitted by Johannes Vandenberg on Tue, 2015-09-01 20:42
I have looked at your first post and could not figure out what the question was. No I have seen the second post and the issue is now clear.
In the detailed resource tab units & prices you set the availability of the unit per time. Thus you only set the availability. This availability is use to determine whether the specific resource is under or overloaded. This is also one on the most important features for Resource Constrained Scheduling and leveling.
This can not be used to define the resources to specific activities. Resource loading is done using the resources tab.
I am budgeting for lower availability of the resources later in the project e.g. In the 1st period of the project the 'Project management' resource is 10hours/day, then reduces to 50% availability (5hours/day) for the second period, and then reduced to 2hours/day availability in the last period. I have done this before for a different project, in an earlier version of Primavera but not sure why its not working now. I have attached picture examples of what I'm trying to do. One is photoshoped.
Member for
10 years 2 months
Member for10 years2 months
Submitted by pradeepronds on Tue, 2015-09-01 16:17
Member for
24 years 9 monthsRaymund,we manage schedules
Raymund,
we manage schedules consisting of many thousands activities and partial resource assignments are not rare
Simple and obvious example - tower crane that is parially assigned to many construction project activities.
In any case if some resource is used at some activity not full work day then the rest work time shall be used on other activities.
Regards,
Vladimir
Member for
15 years 11 monthsVladimir,Your argument is
Vladimir,
Your argument is valid but that depends of the Type of Project.
In a wider complex Project, a Labor resource will be never be assigned any partial hours or days to a certain activity.
Assignment of Partial Labor hrs or days to an activity is what I believe to be applicable only on a very simple Project with not more than 10 Activities.
Member for
24 years 9 monthsIf a resource is used on
If a resource is used on several activities in parallel adjusting resource calendars is poor solution. Besides do you pian to change resource calendars with each schedule update?
Member for
10 years 2 monthsOk thanks for that. I will
Ok thanks for that. I will probably set up a calendar. I just thought there was an easier way
Member for
15 years 11 monthsHi,Max Unit / Time is used
Hi,
Max Unit / Time is used for Resource Leveling Purposes.
THis means, in case you assigned a labor to work in a day more than Maximum Hours per day then it will show you Over allocated Resources. And when Levelling of Resources is applied then it will expand the Duration.
In your case, a separate Calendar for the Labor specifying the Working Hours is needed.
Hope this will clarify.
Member for
10 years 2 monthsThanks Kennan, I attempted
Thanks Kennan,
I attempted this yesterday with no success
Member for
17 years 5 monthsHi Thrainn,Try using resource
Hi Thrainn,
Try using resource dependent activity type instead of task dependent. then assign a dedicated resource for this activity.
May be this will work.
Regards
Kannan
Member for
10 years 2 monthsHi Johannes,How is resource
Hi Johannes,
How is resource loading done using the resource tab?
In the Primavera P6 Professional User's Guide 2011 it has an example for determining resource availibility. This is what it says and based on what I'm trying to do:
'' Example: Determining resource availibility
If the selected resource is one person, a resonable value may be 8 hours (units) per day (duration). In this case, the Max Units / Time would be 8.00h/d, or 8 hours of work per day. Similarly, if the selected resource is a department with 5 people, then the Max Units/Time may be 40.00h/d. This means that 5 people can perform 40 hours of work per day, rather than 1 person performing 8 hours of work per day.''
Instead of increasing the hours per day, I want to decrease it. This feature is'nt working and I don't know why
Member for
15 years 9 monthsHi ThrainnI have looked at
Hi Thrainn
I have looked at your first post and could not figure out what the question was. No I have seen the second post and the issue is now clear.
In the detailed resource tab units & prices you set the availability of the unit per time. Thus you only set the availability. This availability is use to determine whether the specific resource is under or overloaded. This is also one on the most important features for Resource Constrained Scheduling and leveling.
This can not be used to define the resources to specific activities. Resource loading is done using the resources tab.
Regards
Johannes
Member for
10 years 2 monthsI am budgeting for lower
I am budgeting for lower availability of the resources later in the project e.g. In the 1st period of the project the 'Project management' resource is 10hours/day, then reduces to 50% availability (5hours/day) for the second period, and then reduced to 2hours/day availability in the last period. I have done this before for a different project, in an earlier version of Primavera but not sure why its not working now. I have attached picture examples of what I'm trying to do. One is photoshoped.
Member for
10 years 2 monthsTry to insert resource curve.
Try to insert resource curve. Like front loaded or back loaded etc.