Dear all, I want to be updating percentage comple so I rename the "Performance %Complete Colum" as , but when I try to enter a value, it only display 6%, no matter the value it will display 6%.
Please help solve this problem
Thanks
Dear all, I want to be updating percentage comple so I rename the "Performance %Complete Colum" as , but when I try to enter a value, it only display 6%, no matter the value it will display 6%.
Please help solve this problem
Thanks
renamainig a column doe snot effect the functionality of that field
try using duration % comeplete and update that
also what is the duration TYPE set to ?
and what is the activity type set to ?
@Ahmed Aziz, thanks for your reponse.
What you stated is exactly what I did but my problem is anytime I input a value for %complete in the colum, it only dislay 6% alone. e.g, if I type 50% complete for activity, the colum will display 6%. If I enter 20%, it will still display 6%. I don't know why
this is not the proper way to update a schedule
if you are going to use performance % complete then you need to change the % complete type physical
and you need to indicate an actual start date for the activity and then the performance % complete
if the activity is complete you need to indicate the actual finish date
Dear yahya,
if you want to update the percantage complete, you need to know the % complete type for each activity and update accordingly.
here is a better method: show the activity % complete column and update it