14 day rolling calendar

Hi

Does anyone know how to set a 14 day rolling calendar in P6.

Im trying to make it 11 days working 3 days non working.

R
Rafael Davila 👤 Member for 22 years 3 months

There should be a way to model recurring period, rolling calendars are not uncommon.

RollingCalendar photo RollingCalendar_zpsvwh88rol.jpg