Alter Performance % Complete

Hi all,

 

I am a planner based in the Middle East still learning different aspects of Primavera P6.I have a doubt actually which I came across on a previous post in this forum but had no proper answers.

My question is,is it posssible to alter the performance % of a particular activity when we have assigned cost to it?

As far as I understand,

The performance % is calculated as Earned Value Cost = Activity % Complete X Budgeted Cost ( in the baseline )

I tried changing the value of budgeted cost in the schedule but the earned vakue cost recalculates from the baseline once I hit the Refresh button.

 

So is it actually possible to alter the Performance % Complete ( Using any other method )

 

Thanks in advance.

B
Binas Mohamed 👤 Member for 10 years 10 months

Hi Raymund,

 

By altering I mean to show performance % greater than actual.

I have to review updated schedules from some contractors and had doubts on progress recorded for some projects.

 

 

 

 

Thanks

R
Raymund de Laza 👤 Member for 16 years 6 months

Binas,

Would you clarify what do you mean by Alter Performance % Complete?

 

 

Regards,

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts