Hi,
I'd like to sort each level of my WBS by summary Start Date ; like using the "Sort bands alphabetically" option but with Start date..
Is there a way to do that?
Thanks
Gwenael
Hi,
I'd like to sort each level of my WBS by summary Start Date ; like using the "Sort bands alphabetically" option but with Start date..
Is there a way to do that?
Thanks
Gwenael
Hi Gwenael,
You will need to start by abandoning WBS as the fundamental dimension of the layout. (WBS is by its very definition a hierarchical structure for organizing the scope of work, not the schedule. You can't re-sort it alphabetically in the layout either.) While I don't see a giant problem with doing what you want, P6 is just not optimized for it (nor are other tools that I am familiar with).
The simplest approach is to group by Start, with the interval set to month, then sort within each band by start - then finish - in ascending order. You can create activity codes or user-defined fields for organizing your activities independent of the WBS, and some of these might be pseudo-chronological (e.g. Phase1, Phase2, etc., or even "WBS Start Date") Then you could group by these codes before sorting. But like Rafael suggests, that might be more trouble than it's worth for you.
It only sorts the activities in the WBS ; I would like to sort the WBS according to the summary dates of each level.
It only sorts the activities in the WBS ; I would like to sort the WBS according to the summary dates of each level.
I do not use P6 but wonder if by selecting the column title Early Start you can sort by the column value, then you sould be able to save the Layout. The following is the dialog box I get if using Spider Project.
Thank you but it doesn't relly help..
In fact, I would like to keep the same group by options ; but just sort each level of grouping by Summary Start Date, as we can easily do by WBS Name (alphabetically).
Thank you but it doesn't relly help..
In fact, I would like to keep the same group by options ; but just sort each level of grouping by Summary Start Date, as we can easily do by WBS Name (alphabetically).
group by wbs
then by start in the group interval put the internal either day week month
you might have to collapse the wbs to get what you want or select only show summary bars