Hello All , I'm new Here ,Also I'm new in Primavera
Can Anyone help me to understand these terms:
1- Budgeted unit / time
2- Budgeted Units
3- Price /Unit
4- BUdgeted Cost
Thanks in Advance And Best Regards..........
Hello All , I'm new Here ,Also I'm new in Primavera
Can Anyone help me to understand these terms:
1- Budgeted unit / time
2- Budgeted Units
3- Price /Unit
4- BUdgeted Cost
Thanks in Advance And Best Regards..........
1. Budget unit/time = how many units that you expect to use per day 8 hours/day = 1 man or 16 hours /time is 2 men per day
2. Budget Units = Original planned amount of Manhours or Material of units or what ever it is that you are tracking linear feet of conduit. Cubic Yards of Concrete
3. Price /Unit is the price per one unit of what ever it is that you are tracking like one apple $.50 and 2 apples = $1.00
put in the units and the total price is calculated by multiplying the price /unit times the number of units.
4. Budget costs = your original budget cost to perform this activity.