Dear All,
After assigning a resource when I open Project - Resource assignment it is showing blank . Is there any settings that has to be changed inorder to show the resource summary ( Budgeted units) by month. Any thing related to report settings to be modified ?
I already added primary resource column and it is displaying that resource.
Awaitig your valuable reply.
Best Regards,
Sunil.
open Project / Resource Assignments
upper left under layout there is a small upside down triangle click on it
select filter and make sure that you have the correct filter set
also same place for columns select default
Zoltan,
Resource usage profile is working fine, problem is that when we open Project / Resource Assignments ..it is not displaying anything. Any Report settings we have to change or not.
Best Regards,
Sunil.
if you have assigned a resource to all of your activiites you can select view show on bottom and select resource usage profile
then on the right hand side click resource usage profile options
in the data tab make sure that units is checked
in the graph tab make sure that calculate average is checked and that Base on hours per time period is checked
right click the graph area and select timescale and select Year/Month as the time interval
Hi Vladimir,
The software is P6 Ver 7.1
Best Regards,
Sunil.
Hi Sunil,
I can answer to your question explaining where to find all the data on resource assignments in Spider Project. It looks like you mean some other software. Is it present in the discussion forums here? PP has forums on P6, P3, MS Project, Asta, Sciforma, etc. Please specify the software that you use if it is absent in the PP list or put your question in the discussion forum on your software.