Load Labor Units/ Manpower in an Updated Schedule

Dear Friends,

My Client is asking to load resources ( Manpower ) in the existing Primavera Schedule (P6)  which is already updated . I have never came across such situaion  and am not sure , technically can it happen. Can ayone shed some light on this.

Thanks,

Deepak

Z
Zoltan Palffy 👤 Member for 16 years 10 months

my answer reains that same 

add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress 

for your activiites that are completed update the reamining units as zero

D
deepak khundrakpam 👤 Member for 15 years 7 months

Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!

Thanks in advance!!

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yes you can do it add a resource in the resource dictionary 

then add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts