HI ALL PLEASE I NEED HELP DEVELOPING A BRICKS CLADDING PROGRAMME AS AGAINST THE TRADITIONAL BUILD ONE
NEEDS HELP ON DEVELOPING A PROGRAMME
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Kay
It is like any other cladding system.
It all depends on the structure - Insitu concrete or steel.
Next you need to consider the Secondary support system - usually steel angles.
Is the alingment top down or bottom up?
Are the panels hung or bolted?
You also have to take into account the safety aspect regarding scaffolding and fans. Who is working overhaed.
It is unlikely that brick cladding panels wil be fixed from the inside so are they fixed going up or down?
The next consideration is when does the structure get to be weathertight.
I doubt if that has answered your question but maybe it has given you something to think about.
Best regards
Mike Testro
Bricks Cladding Programme technique as against the traditional one.