1. While importing from XL, Actual Dates are updating and Physical % Complete is not updating
2. Even If Physical % complete is updated manually, Remaining Duration is not changing
3. Actual Expense cost is also imported, but not updated in Schedule
Any body please help in this regards. I doubt i am missing some important step in the process of importing. Any body can help me mentioning step by step procedure for successful import
make sure that % complete type is duration and export the duration % complete the actula start date and the actual finish date to excel update the three items in excel and import back into p6
first make sure that you have the proper rights to import information
1. you can only import actual dates, and constraint dates and these dated need to have the correcr format was well as the correct TIMES. Physcial % complete must be in the correct format. Why not export an activity with these items and use it as a template for importing the new information.
2. That is correct when using physical % complete it DOES NOT update remaing duration because remaing duration is assoicated with duration % complete. In order to use physical % complete to update remaining duration run a global change where duration % complete equals physical % complete
3. make sure that the format is correct