Thanks Zolton for that reassuring and confident manner in noting pressing F9 will not work this way. I will have to check if soemthing is wrong somewhere.
Thank you.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2015-06-03 16:26
Member for
10 years 5 monthsDear Anthony Obasi, IT IS
Dear Anthony Obasi,
IT IS IMPOSSIBLE THAT PRESSING F9, ADDS ACTUALS TO THE PROJECT.
You must be using " APPLY ACTUALS"
You need to play around Calenders to see if it causes any abnormality.
Regards,
“For more queries, you can always contact me here or in person:ce.arslanshahid@gmail.com”
Arslan Shahid
Member for
10 years 5 monthsThanks Zolton for that
Thanks Zolton for that reassuring and confident manner in noting pressing F9 will not work this way. I will have to check if soemthing is wrong somewhere.
Thank you.
Member for
16 years 3 monthspressing F9 would would NEVER
pressing F9 would would NEVER make the activity have an actual start date unless you check the actual start box or unless you
select “Apply Actuals: from the tools selection.
Member for
21 years 8 monthshttp://www.cpmsolutions.ca/au
http://www.cpmsolutions.ca/auto-compute-actuals-vs-update-progress/