P6 Scheduling (F9)

Hi all,

I need help on P6 scheduling. I have a project which starts on Dec. 2015 and after inserting the activities I press F9 and selecting data date which is in Dec. 2015, the activity is registred as having started as I see on the activity information that the start box is checked and the activity bar has changed. My question, why would the F9 (scheduling) make the project to start when the date is a future date?

You comments are appreciated.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

pressing F9 would would NEVER make the activity have an actual start date unless you check the actual start box or unless you 

select  “Apply Actuals: from the tools selection.