Hi All
I Would like to include a narrative of my schedule with the tender schedule. I am wondering if any of you would be able to point me to a sample tender schedule.
Also it would be great to hear tips and best practise you follow whilst preparing and submitting tender schedule.
Thanks in advance
Sachin Martin
Hi, Sachin.
This is not what you were looking for -- but I sincerely believe that,in general, adding computed drag totals for all critical path activities would render any schedule more credible and show that the person who prepared it is knowledgable of the most modern scheduling techniques.
I would actually take it one step further by showing Version 1 and Version 2:
I can't think of a quicker or better way to demonstrate scheduling competence.
Fraternally in project management,
Steve the Bajan
www.TotalProjectControl.com