Ahead of Schedule Activities

Hi guys,

My project is in the middle and i have some activities completed, mostly activities status is in progress. Some body help me on:

1) I want number of in progress activities that are ahead of the schedule.

2) Number of in progress activities that are behind the schedule.

3) Number of in progress activities that are on schedule.

Some one tell me the filter for above listed requirement

 

S
Sunil Babu 👤 Member for 15 years 6 months

Hi Hafiz,

Also you can check, variance with BL finish dates. Activities with -ve values indicates behind schedule and those having +ve indicates ahead of schedule.

Best Regards,

Sunil.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

sorry did it off the top of my head

here it is 

then filter #1 activities ahead of ahead of schedule 

ANY

where variance BL project start is less than start 

or 

where variance BL project finish is less than finish 

filter #2 behind schedule 

where variance BL project start is greater than start 

or 

where variance BL project finish if greater than finish 

filter #3

where variance BL project start is equal to start

or 

where variance BL project finish is equal to finish

H
Hafiz Khalid Hussain 👤 Member for 13 years 11 months

Dear Zoltan,

Thx for your concern, but i check your method and "Variance BL Project Start" is not available in filters. Actually it is available in "parameters" but not under "value". Kindly further guid

Z
Zoltan Palffy 👤 Member for 16 years 10 months

1st add a column for number of activities its under number of activities then select activity count

then under group and sort check show group totals and show grand totals

you must maintain and assign a baseline

then filter #1 activities ahead of ahead of schedule 

ANY

where start is less than variance BL project start

or 

where finish is less than variance BL project finish

filter #2 behind schedule 

where start is greater than variance BL project start

or 

where finish is greater than variance BL project finish

filter #3

where start is equal to variance BL project start

or 

where finish is equal to variance BL project finish

 

another way

filter #1

total float is greater than 0

filter #2

total float is less than 0

filter #3

total float equal 0

 

but I suspect you want the first set of parameters 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts