Client Claim Tenability evaluation

Member for

11 years

Hi everyone. Hope u all are keeping well.

Our Company trying to Standard the Project Schedule WBS. The Objective is that the Initial detailed scheduled WBS will be same across organization and the same WBS will be uploaded in EIP. Any platform like DPR, WPR, Cost Recon, Cost packages, NAVIS work, P6, Safety and Quality will take the required WBS from the WBS Master. It will be generic and only the nomenclature could be changed based on Projects. (e.g. Airports, Residential High rise, Hospital, IT & Office Space, Mall etc.).Please suggest some industry standard or some suitable one..

Regards

Somenath Acharya

Member for

11 years

Hi everyone. Hope u all are keeping well.

Our Company trying to Standard the Project Schedule WBS. The Objective is that the Initial detailed scheduled WBS will be same across organization and the same WBS will be uploaded in EIP. Any platform like DPR, WPR, Cost Recon, Cost packages, NAVIS work, P6, Safety and Quality will take the required WBS from the WBS Master. It will be generic and only the nomenclature could be changed based on Projects. (e.g. Airports, Residential High rise, Hospital, IT & Office Space, Mall etc.).Please suggest some industry standard or some suitable one..

Regards

Somenath Acharya

Member for

11 years

Thanks Mike. We have settled the claim as per Indian Contract Law as advised.

Member for

19 years 10 months

Hi Somenath

If you have been paid for 15mm plaster but have installed 12 mm plaster then obviously the rate has to be adjusted.

This is apart from the debate about the suitability of the thinner plaster in a domestic environment.

If the Contract is insufficient in this case then your fall back is the India Contract Act 1872 which over rides the Contract.

Best regards

Mike Testro