Loaded Costs are not spreading in the activity's duration

C
Celso Paman 👤 Member for 16 years 4 months

Dear Experts,

We have a program fully loaded with cost and manpower. The problem that we are facing right now is that lots of costs that were loaded to the program are not spreading to the entire duration of the activity. 

Can anyone share his knowledge on resolving this issue?

 

capture.png

Thanks in advance.

Celso

Z
Zoltan Palffy 👤 Member for 16 years 10 months

on the left try changing the column to early start and early finish instead of just start and just finish

check to see if the Drive Activity Dates by default option has been switched off. Make sure that the calendars match down to the exact workhours, because even if a resource assignment is ending on the same day as the activity, if they are out of sync by even 1 hour, then the resource assignment will no longer sync up with the Activity's dates. Make sure you have your Duration Type set to Fixed Duration and Units/Time or Fixed Duration and Units.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that your resource is using the same calendar as your activity. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts