P6 version 7 - major bug!

A
alex ebner 👤 Member for 21 years 4 months
A
Arnold Puy 👤 Member for 19 years 1 month

Hi Alex,



Actually, I already discovered this from the first day of my installation and I also post this issue here:



http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=6429…



This known problem in Project Management is currently under review and may be corrected in a future release.



Solution ID: prim84262

Calculate Average is not working in the Resource Usage Profile in P6 v7



Regards,



Arnold

R
RJ Rivera 👤 Member for 21 years 9 months

ALex,





It Worked on my System, I have P6 Version 7 installed and had my Average divided by the interval I specified.