Import Resource Usage Assignment Spread back into P6

Hi,

I have a list of resources and their budgeted hours on a monthly basis in excel and would like to import this list into P6.

In P6 i have the list of resources which already have actual hours accrued as well as remaining hours.

 

The requirements are as follows:

1. To ensure that the resource usage spread on a month by month basis  from P6 tallies with that in Excel.

2. Minimal effort to ensure the two reports tally.

 

I was wondering if anyone here has faced similar requirements, and how you have gone about resolving this.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

one way to do this is to use the period close out function which closes out the manhours for that updating period and escentially is like balancing your checkbook so that each month the actual units this period always starts with zero. So when you are importing the actuals they are only for the update period. When you perdform a period colse out it rolls the actual this period amounts into the actual to date period and set this period to zero.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts