Dear All,
What will be the effect of updating an out of sequnce activity in a Baseline programme (Cost loaded) in a Villa Project.
Planned dates of that activity falls in the month of May, but actvity completed in the schedule period. (Schedule % is 0, Activity % is 100).
How will it affect the Performance % ?. Settings for EV calculations are as follows.
1. Performance % equal to Activity %
2. ETC is equal to remaining cost.
3. Budgeted values with current dates.
4. Progress override
Best Regards,
Sunil.
Zoltan,
Thank you, I have added the actual cost manually.
Best Regards,
Sunil
the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab.
The actual cost have to be updated manually but the units wil be updated
the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab.
The actual cost have to be updated manually but the units wil be updated
Zoltan,
Already updated with actual start and actual finish.
Using percentage complete type - Duration percentage
Regards,
Sunil.
are you putting an actual start and an actual fnish DATES on the activities ?
what type of percent complete are you using ?
Dear Experts,
After updating the Baseline , Actual budget cost of many of the activities not displaying.( Activities which are having schedule percentage - 0% but activity percentage -100%) . Why it is happening.? Actualy those activities 100% completed during the schedule period.
This is affecting the EV calculations.
Your reply will be highly appreciable.
Beast Regards,
Sunil.