K
Kannan CP 👤 Member for 17 years 11 months

Dear All,

Is it allowed as per FIDIC, for a Contractor to submit the detailed claim (WITHOUT A NOTICE) within 28 days after the Contractor became aware of the event.

For eg: the Contractor submitted the impacted schedule with delay event/supporting documents soon after they became aware that the Employer delay is started affecting the Contract Completion date. 

Can the Emplyer reject the claim by saying that the Contractor didn't submit the notice of delay and directly submit the claim with the TIA programme.

 

Regards

Kannan