Dear Planners,
I got encounter this kind of problem when I undergone a recovery plan to my project, of which after finalizing the schedule I exported the resources to get the resource planned based on the activity loading. I found out that the dates are not matching with the activity dates. May i lend your ideas how to manipulate this error.
Thank you,
cecil
Cecil,
I experienced the same and my workaround is Remove the Resources and reassign again. It may occur in a few resources though.
Regards,
Hi Guys,
Thanks for your ideas, but I used the same calendar for the activities and resources. P6. V.07 am using..
Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.
So old no longer Photobucket pictures aer available.
It may be that your resource calendars are different to your activity calendars
It would help to know what software you are using, though.