What is effect during updating, if the duration unit is differ from resource units? i.e. if the duration unit is in “days” and the resource unit is in “Hours”?
I am working in P5.I work out program in in my system and import XER to another system. The issue is there is some difference in the labour units. The difference 0.8 times than older value. I have checked the calendar assignment and user preference all are same as in my system. Please advice how to rectify the issue.
Salman,
Check your Time Units setting. It maybe set to day but the xer that you importing is set by hours or vice versa. Check also your calendar if set 10hrs per day.
Select Edit->User Preferences-> Time Units tab. Check the Unit of time.