Labour units reduces

C
chidhambarathanu Bala 👤 Member for 13 years 1 month

What is effect during updating, if the duration unit is differ from resource units? i.e. if the duration unit is in “days” and the resource unit is in “Hours”?

C
chidhambarathanu Bala 👤 Member for 13 years 1 month

I am working in P5.I work out program in in my system and import XER to another system. The issue is there is some difference in the labour units. The difference 0.8 times than older value. I have checked the calendar assignment and user preference all are same as in my system. Please advice how to rectify the issue. 

R
Rodel Marasigan 👤 Member for 19 years 7 months

Salman,

Check your Time Units setting. It maybe set to day but the xer that you importing is set by hours or vice versa. Check also your calendar if set 10hrs per day.

Select Edit->User Preferences-> Time Units tab. Check the Unit of time.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts