Hi all,
When I track my physical progress i follow this way: after i assign resources to primavera(manhours and materials) i define 1$/h unit price for manhour resource so budgeted labor units gets equal to budgeted total cost . anyway when updating as per baseline i can track physical progress perfectly from earned value and performance % complete columns.
But now i wanna track also project cost complete in the same project %(as per Contract BOQ) separately in primavera including labor and material cost ..
Is there any way to do it?
Thanks in advance
Mujdat Ozacar
tracking physical % complete & % cost complete separately in the same project
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
you already have Budgted total cost and Budgted Units
for your actual costs you can run a global change where actual costs equals Budgeted cost * % complete
for actaul manhours you can run a global change where actual units equals Budgeted Units * % complete