tracking physical % complete & % cost complete separately in the same project

Hi all,



When I track my physical progress i follow this way: after i assign resources to primavera(manhours and materials) i define 1$/h unit price for manhour resource so budgeted labor units gets equal to budgeted total cost . anyway when updating as per baseline i can track physical progress perfectly from earned value and performance % complete columns.

But now i wanna track also project cost complete in the same project %(as per Contract BOQ) separately in primavera including labor and material cost .. 

Is there any way to do it?



Thanks in advance



Mujdat Ozacar

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you already have Budgted total cost and Budgted Units 

for your actual costs you can run a global change where actual costs equals Budgeted cost * % complete

for actaul manhours you can run a global change where actual units equals Budgeted Units * % complete

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts