Require Activity % Complete equal to Expense % Complete

I
Irfan Khan 👤 Member for 16 years 10 months

Hi to all experts,

 

I am using Primavera P6 R8.2

 

Here i am working with the schedule with 4,000 activities & almost 2,200 activities i have loaded Cost though Expenses.

The Problem i am facing that for example : one activity having 50% of  Activity % Completed so far, but when i am looking @ the Expenses Tab & its not showing me any actual cost for the same activity. Even i have tried to Import & Export throuhg excel in order to reflect the Activity% complete into Expenses % compete but due to (*) sign the values in exel sheet cant be modified.

 

Please anyone can help me in this regard.........i will be highly obliged  

 

I
Irfan Khan 👤 Member for 16 years 10 months

Thank you Mr. Zoltan.......... i got what i was looking for.

I
Irfan Khan 👤 Member for 16 years 10 months

i tried to resolve it through Global Change......but unfortunately i didnt get way to fix it.... :(

A
Ahmed KHR 👤 Member for 15 years 6 months

Hi Irfan,

 

Try to use global change (Expense % = Activity %)

 

Regards

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts