Earned Value Cost Error In P6

Hi Everyone, 

 

Can anybody help with a problem I'm facing witht the EV Cost in my P6 V7.0

 

When Updating my After assigning resource -> Modyfing Budgeted toal COst for this resource ->Dismarking Auto Compute actuals and Calculate Cost from Units -> Setting % Complete Type to Physical -> Givind Start Dates and Modifying Percentages -> No Changes are reflected in my Earned Value COst !!

 

Can Somone help me plz in this issue cuz I've been trying almost everything and none is working !!

 

Thanks,

Mohamed El-Dawy

Z
Zoltan Palffy 👤 Member for 16 years 10 months

look under admin preferences 

look at the Earned Value tab 

what are your setings for Technique for computing performance perecent compelte  ? (Activity % Comeplete)

what are your settings for Technique for computing Estimate to Complete  (ETC)  ? (ETC = remaing cost for activity)

what are your settings for Earned Value Calculations ? (Budgeted values with Current Date)

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts