Inflation in Primavera P6 V8.3

A
Ahmed Aziz 👤 Member for 11 years 9 months

Hi all,

I am want to know how primavera calculates the inflation provided that I have reflected the inflation in the resources as in the screen shot below and the resource is made to account only for the money (the total cost of each activity is calculated in excel in seperate files and then is added to this resource on each activity)

Resource Inflation.png

Thanks,

A
Ahmed Aziz 👤 Member for 11 years 9 months

thanks zoltan for your reply,

I think i am getting to know how it is calculated, but i want to give you full details on how I assign the budget to the schedule.

I have made:

  1. a non labor resource and named it "Cash"
  2. this resource has the units as in the screen shot in the first topic in the thread
  3. I have assgined this resource to the activities where inflation will occur
  4. I have put each activity budget (calculated by the cost team) in the budgeted non labor units
  5. the primavera calculates the budgeted cost by multiplying the budgetd non labor unit * standard rate

I want to know how this will impact the calculation, as I have made an exercise to see how the inflation is applied. I have made a four year activity to see the distribution of the budget on it. and I have made 4 one year activities as in the screen shot below

[[wysiwyg_imageupload:2359:]]

the total is not the same and the distribution is not the same, any help with this issue

A
Ahmed Aziz 👤 Member for 11 years 9 months

thanks zolton for your reply,

I think i am getting to know how it is calculated, but i want to give you full details on how I assign the budget to the schedule.

I have made:

  1. a non labor resource and named it "Cash"
  2. this resource has the units as in the screen shot in the first topic in the thread
  3. I have assgined this resource to the activities where inflation will occur
  4. I have put each activity budget (calculated by the cost team) in the budgeted non labor units
  5. the primavera calculates the budgeted cost by multiplying the budgetd non labor unit * standard rate

I want to know how this will impact the calculation, as I have made an exercise to see how the inflation is applied. I have made a four year activity to see the distribution of the budget on it. and I have made 4 one year activities as in the screen shot below

[[wysiwyg_imageupload:2359:]]

the total is not the same and the distribution is not the same, any help with this issue

Z
Zoltan Palffy 👤 Member for 16 years 10 months

if you have calculate costs from units checked then it will take your standard rate for that day multiplied by the manhours scheduled to be perfomed for during that time frame. 

All manhours scheduled to be performed in 2013 will be multiplied by $1.00 so 50 manhours * $1.00 equals $50.00 for those activities

All manhours scheduled to be performed in 2014 will be multiplied by $1.00 so 50 manhours * $1.00 equals $50.00 for those activities

All manhours scheduled to be performed in 2015 will be multiplied by $1.07 so 50 manhours * $1.07 equals $53.50 for those activities

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts