Hello everyone,

I was just wondering how to load the resident resouces of a project ?! I mean, like the site engineer for instance, he has to be involved with each and every activity, but on the same time i don't want to load a "site engineer" resource to each and every activity! What i actually do is load these "resident resources"; like, admins, site engineers, foremen, supervisors, and even PM's to the critical activities along the critical path, but that changes during the progress of the project.

My question is what is the right way to load resources who are assigned along the whole project from start to finish?!

Thank you very much in advance and merry Christmas - also in advance :).

Wadi

Z
Zoltan Palffy 👤 Member for 16 years 10 months

agreed use LOE from the start of the job to the end of the job for indrect resources

G
Gary Whitehead 👤 Member for 17 years 2 months

Hi Wadi,

 

Asuming resource levels will remain constant throughtout the project (ie 1 x site engineer from start to finish of the project), then you should create an LOE activity stretching across the project duration, and load your indirect resources such as site engineer, planner, etc onto it.

 

Cheers,

 

G

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts