Hello,
can you please help me to figure out why some subtitled activities were disappeared when i baselined the project or even when i want to save the project,they were missed
first,i maintain the the baseline
then i assign baseline
and some of my activities were diappeared in current project and also in baseline project.
thanks,
this is the wrong forum
there is no such thing as subtitiles it is how you code and group your activities that give the different levels of banding