I am a new user in primavera p6, please can some one to show me how to display on the gant chart the resources assigned for each activity beside the bar.
Thank you
I am a new user in primavera p6, please can some one to show me how to display on the gant chart the resources assigned for each activity beside the bar.
Thank you
that is incorrect you do not need to make a udf
just go to the bars and select current bar labels
then click on the bar lables tab
then select add
then in the position select right
clikc in the label area look in the drop down and select budget labor units for rmanhours or budget labor cost or whatever you want to show there
Amar,
Copy the Resources into a UDF then use it as Bar Label.
Regards,