to display resources in the gant chart

I am a new user in primavera p6, please can some one to show me how to display on the gant chart the resources assigned for each activity beside the bar.

Thank you

Z
Zoltan Palffy 👤 Member for 16 years 11 months

that is incorrect you do not need to make a udf 

just go to the bars and select current bar labels 

then click on the bar lables tab

then select add 

then in the position select right 

clikc in the label area look in the drop down and select budget labor units for rmanhours or budget labor cost or whatever you want to show there