Primavera P6 V7.0 resource data export to xl

Hi Guys

Appologies if this is an old chestnut but I have just moved jobs and using P6 V7 for the first time.

Also new to this forum

I am struggling to get the resource allocation data out of P6 and into xls

Tried the wizard but still no joy

Could anyone point me in the right direction

Many Thanks

JD

R
Raymund de Laza 👤 Member for 16 years 6 months

John,

As Johannes suggestion... in Resource Assignment pane you can have a layout that shows all Resources with corresponding activities where it was assigned or the other way.

regards,

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi John

Go to the  top left side of your screen and seek "Resource assignments". Here you seen all the resource assingments . You can now filter for budgeted or remaining. Seclect, copy and past. This shoud do.

Regards Johannes

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts