Subcontractor's Schedule Imported but no Actual Earnings

Hello,

I have received and imported an update from a subcontractor which has actual progress for activities.  My problem is that their actual material and labor resources are all zero's.  We have both shared screen shots and in his schedule he has values for the actual material and labor.  I do not have any of those actual resource values that he is showing me.  I know that he is sending me the correct file and my resourece settings are as follows.

Labor Resource

Details = Auto Compute Actuals is checked.  Calculate costs from Units is checked.

Units & Prices = Price / Unit = $0.00

Material Resource

Details = Auto Compute Actuals is checked.  Calculate costs from Units is checked.

Units & Prices = Price / Unit = $1.00

My instinct tells me that the problem was in my Price / Unit.  I thought that my Price / Unit would have to match his Price / Unit but I have changed these values and nothing changes after scheduling.  My understanding is that he should have all values entered accordingly and send me the file.  After importing I SHOULD be seeing the same actual dollars and hours that he has regardless of the Price / Unit settings.

Any help is very much appreciated.  I have not seen this problem before.

Thanks,

Brandon

 

 

 

B
Brandon Wall 👤 Member for 11 years 7 months

Thanks for the help Raymond.  That was an easy fix and lesson learned.

R
Raymund de Laza 👤 Member for 16 years 6 months

Brandon,

During import go to options of importing new resources instead of update existing which was set as default.

regards..

R
Raymund de Laza 👤 Member for 16 years 6 months

Brandon,

During import go to options of importing new resources instead of update existing which was set as default.

regards..

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts