SChedule Behavior

In my (construction) programme (P6 v7) three Level of Effort activities in the second level of WBS are linked with the first activity “Commencement of the Project” with “SS” relationship and the last activity of the project “Project Completion Date” with “FF” relationship i.e. the whole project and showing a duration 610 days each the WBS summary also showing 610 days.

The calendar of these activities are “6 Days a Week”.

The activities related to the Client, Engineer, and the Local Authorities have “5 Day Work”

The engineering and procurement activities have “7 Day Work” calendar.

All the construction activities have “6 Days Work” calendar.

I could not understand this behavior of the schedule but I have to explain this to my Client’s planner, can anyone help me?

Cheers

H
Heping Xiao 👤 Member for 20 years 11 months

Hi,

 

You should change your LOE acitivity calendar same with your WBS. Because your activities have differen calendars, WBS will choose the proejct default calenda, which is ste in Project details tab.

 

BR

Heping

Z
Zoltan Palffy 👤 Member for 16 years 11 months

a LOE activity will span from the start date of the predecessor SS activity to the end date of the successor activity FF 

its calendar and wbs does not matter 

what behavior are you questioning ?

D
Dieter Wambach 👤 Member for 19 years 5 months

Tanveer

I don't really understand your question.

The duration of LoE and of WBS-summary activities is defined by other activities. This is independent from their calendar. WBS-summary spans over a wbs-element.

Projects with different locations frequently work with different working contracts. In addition you have local holidays etc.

Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts