Resources on LOE Activities

U
Utku Çil 👤 Member for 15 years

Hi there,

I am trying to set up a detailed schedule for an infrastructure project nowadays and my problem is about assigning a resource (say, Project Manager) to a Level of Effort activity. When I assign the resource to the activity, the budgeted units value is distributed uniformly over the duration of the task. However, I do not want to have it that way, so I go to the resource assingment window and manually adjust the manhour for each day. So far so good.

My problem begins when I schedule the program. As soon as I press F9 and run the schedule, all the adjustment I manually made on the manhours assigned to the LOE activity has gone. Again, P6 distributes budgeted units over the task span and I return to the beginning.

Is a there way that I can fix the manhours (manually adjusted) assigned to the LOE activity?

PS: I am still in the planning phase. So, no actual units/costs has been presented in the schedule.

Thanks in advance.

Regards.

Utku

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Utku

The way you assign the resources in my opinion doesn't fit to LoE - fixed versus variable duration. If you'll use an activity with a fixed duration, a curve will - roughly - work.

A resource-curve for LoE won't be reliable.

An assignment by period is only possible in the web-based user interface - to which you should have access.

Regards

Dieter  

Z
Zoltan Palffy 👤 Member for 16 years 10 months

why not assign a curve to the resouce for the LOE to have it distrubite budgeted unts the way that YOU want it ?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts