I have just started on a project. When I review Budgeted resource hours on the activity they are 8 times higher that what the other planner sees. How do I resolve ?
Resource hours
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Sometimes this happes when you convert a p3 project to p6
1. check your resource default units/time it would be 8
to fix this run a global change
where budgeted units is greater than 8 then
budget units equals budget units / 8