Resource hours

I have just started on a project. When I review Budgeted resource hours on the activity they are 8 times higher that what the other planner sees. How do I resolve ?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Sometimes this happes when you convert a p3 project to p6 

1. check your resource default units/time it would be 8

to fix this run a global change 

where budgeted units is greater than 8 then 

budget units equals budget units / 8