HI,
I am a relative novice to planning and construction. At the moment I am carrying out a project planning programme for the construction of a school, using Primavera. Contract duration 18 months at a cost of £8million. I have assumed a plan size area of 3000m/squared.
I would appreciate if anybody could give some advice on the basic activities, their order and the RELATIVE DURATION it takes for each.
The programme has to comprise of at least 60 activites. Is it easier to just group all one type activity together ie. plasterboard and assign it the total cost for the whole project in Primevera.
Below is the outline of my schedule so far but I am not really happy with it as I don't know what half the activities really are!
Any advice on where to look for examples or advice on my order of schedule so far would be greatly appreciated!
Many thanks!
Stay Classy, Ross
TASK/ACTIVITY
START PROJECT
SITE PREPARATION
Construct Perimeter Wall and Secure site
Site Excavation
Set out and level site
Enabling works (Portakabin erection etc.)
Mains Connection for Tools
FOUNDATION/SUBSTRUCTURE
Hire Scafolding
Erect Scafolding
Excavate and lay all underground services
Footings
Dig Footing and install reinforcingg
Pour Footings
Pin Footings
Stock Block, Motor, Sand
Build Block Foundations
Erect ground beams
Ensure ground drainage system
Excavate for pipeworks
Buy pipeworks and steelworks
Install Pipeworks
SUPERSTRUCTURE/STEEL CONCRETE WORKS
Erecting structual steelwork
Timber framing
Metal profiled sheet decking
CLADDING/COVERING
Rainscreen cladding
Sheet/Board cladding
Concrete slab cladding
Waterproofing
WINDOWS/DOORS/STAIRS
Windows
Doors
Stairs
Glazing
SURFACE FINISHES
Plastering
Tiling
Coating paint to protect steelworks
ROUGH CARPENTARY
Frame walls
Install wood/plythwood
Roofing
Install pipeworks
Install gutters
roof glazing
roof slating
Plumbing
Procure pipeworks
Install Pipeworks
Water connection
Install toilet/handbasins
ELECTRICAL
Lighting
Alarm System
Telephone/TV System
Heating requirements
AC installation
INSULATION
Air tight strips
Double Glazing
DRYWALL
Stock drywall
Hang drywall
tape and finish drywall
Sand drywall
inset wall partitions
PAINT AND VINYL
Prime Coat
Finishing Coat
LANDSCAPING
Carpark
Pavements
Patios
Playground
Gardens
FINISHES
Plumbing
Electrical
Paint touch up
CLEAN UP
Clean up and demobilize site
Final Walkthrough
PROJECT FINISH/COMPLETION
TOTAL
I THINK IT MAY OUT DATE.
But someone can help this post...........
here r some activites.............