Can anyone tell me how P6 handles the original duration while an activity is Resource Driven vs Task Driven ? The Activity Calander is 7x24x2 while the Resource Calander is 5x10x1.
Resource Driven Activities vs Task Driven Activities & how it effects Original Duration
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Thanks Mike...
If an Activity is Task Driven the Original Duration for that activity may be 4 as displayed in the original duration field. Change the activity to Resource Driven and the original duration as displayed will change. I know why it changes, but what I am trying to do is to get it to display the 4. The client wants to see the "Activity Original Duration" not the "Resource Duration". I have a very difficult time trying to write and explain what I am asking. It is a big weakness. If you can understand me, I would appreciate any help. Thanks
Hi Richard
Normally the resource driver over rides the task.
This leads to all sorts of confusion if the two are out of sync - best keep them the same.
Best regards
Mike Testro