Dear Superiors,
Can any one assist me on the above subject Please !
I have a Labor type Resource Name – Dozer Operator whose Budgeted Units are = 464.
Non labor type Resource Name – Dozer who’s Budgeted Units are = 0.
Here my question is !!
Is there any way to equal those Dozer Operator Budgeted Units 464 to Dozer while Using Global change in P6 v 7 .
Thanking you and Regards,
Wasiuddin.
if budgeted non labor units equal 0
then budgeted non labor units equal budgeted labor units
in the global change make sure that the Select Subject Area up top is set to Activity Resource Assigments
I am also looking for the answer of same question, how to equalize budgeted labor unit to budgeted nonlabor unit using global change or any other way?