Resource Lag & resource multiplication

Hi, Every body 

How could i assign a resource with a certain lag for a particular activity ?

Then is there a way to make multiplications in resource assignment ( ex, to assign 3 workers for an activity , h repeat assignment trible which i believe it's ot practical ) ?

Thanks in advane

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Essam

i don't know a multiplicator. You'll have to select twice , triple, ... The units are taken from the resource's default units

For a choice by profession, study the chapter of the role concept in your reference manual.

Regardss

Dieter

E
Essam Yassin 👤 Member for 12 years 5 months

Thanks Wambach

The forst question ( Resource lag ) i got it yasterday

But for second one, i know that i can add whatever resource to an activity . My point is how to avoid clicking the same resource or role while assignment ? Specially that i add resources (Manpower ) by proffesion not by name ?

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Essam

This is from the P6 Help:

Original Lag (in the resource tab)

The planned time lag between the activity's planned start date and the resource's planned start date on the activity. If the resource is planned to start work when the activity is planned to start, the planned lag is zero.

You can assign a resource as often as you need - if allowed under project --> tab resources.

 

Regards

Dieter

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts