Here i am wondering a way to assign weights to my entire activities as well as WBS level.
My schedule is loaded with Man-hours but now my Client asking to show the weight on the schedule.
I have checked in P6 & there is no any default column i found where i am able to show the weights, but i guess by the help of UDF we can show those weightages.
any reply in regard will be highly appreciated.
Thanks in advance .... :)
Hi Irfan
I'm not sure if I understood right.
Weight in P6 is given by budgeted units (labour or non-labour), material units or costs (labour, non-labour, material, expenses) or the sum.
In the Activity Usage Profile you can easily create the s-curves. A better formatting would be in Excel or any other spreadsheet: Create a report in csv format --> read into Excel --> format the graphics --> print.
If you'll need an explicite weight independent from budget (but why?) you can use a UDF.
If you'll mark "Show Grand Totals" in Group&Sort iP6 will sum up.
Good luck with your planning
Dieter