Here i am wondering a way to assign weights to my entire activities as well as WBS level.

My schedule is loaded with Man-hours but now my Client asking to show the weight on the schedule.

I have checked in P6 & there is no any default column i found where i am able to show the weights, but i guess by the help of UDF we can show those weightages.

any reply in regard will be highly appreciated.

 

Thanks in advance .... :)

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Irfan

 

I'm not sure if I understood right.

Weight in P6 is given by budgeted units (labour or non-labour), material units or costs (labour, non-labour, material, expenses) or the sum.

In the Activity Usage Profile you can easily create the s-curves. A better formatting would be in Excel or any other spreadsheet: Create a report in csv format --> read into Excel --> format the graphics --> print.

If you'll need an explicite weight independent from budget (but why?) you can use a UDF.

If you'll mark "Show Grand Totals" in Group&Sort iP6 will sum up. 

Good luck with your planning

Dieter 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts