NUMEROUS ADDITION OF WORK TO BASELINE PROGRAM

Hi, I have been working in a Project with duration of 9months, supposed to complete by Sep'13. Due to various alterations in the Finishing Schedule and Nomination of new works, the project has been dragged till date, with every day addition of new works.

Now, the Management has asked us to submit an impacted program for depicting delay incurred, basically for claim.

Kindly advise, what should be the approach as the baseline program has nearly lost its orginality due to numerous changes.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Gary

Time is not at large if there is a contractual mechanism to award an EoT for extra work ordered by the client AND the client abides by it.

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 3 months

If the client is adding new scope daily, after the contractual completion date, is time not at large?

M
Mike Testro 👤 Member for 20 years 6 months

Hi Mohamed

Welcome to Planning Planet

Step 1 Save the original (not progressed) baseline as a new file called Extra Work.

Step 2 Add the new work as individual tasks and arrange the logic.

Step 3 Reschedule - This will give you the revised completion date and EoT entitlement

Step 4 Add the original progress - this will provide a Time Impact Analysis for cost and concurrency.

Best regards

Mike Testro

Forum Sponsor

Top Posters

David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts