Oracle Primavera - PM6 Member for 11 years 3 months Member for 11 years 3 months Submitted by Ravi Katare on Thu, 2014-07-17 12:09 Permalink Hi,It generally pertains the Hi, It generally pertains the no's of hours the resource required to complete the task on that day But, If you select calculate average checkbox in spreadsheet option, then it will be average figure based on your defined value. - Ravi Log in or register to post comments
Member for 11 years 3 months Member for 11 years 3 months Submitted by Ravi Katare on Thu, 2014-07-17 12:09 Permalink Hi,It generally pertains the Hi, It generally pertains the no's of hours the resource required to complete the task on that day But, If you select calculate average checkbox in spreadsheet option, then it will be average figure based on your defined value. - Ravi
Member for
11 years 3 monthsHi,It generally pertains the
Hi,
It generally pertains the no's of hours the resource required to complete the task on that day
But, If you select calculate average checkbox in spreadsheet option, then it will be average figure based on your defined value.
- Ravi