Disappearing Budget values

J
John Revere 👤 Member for 11 years 11 months

The resource calendars are a mess and Im wondering if this is an issue as when an actual start date is entered to status the actvitiy the resource cost value is erased immediately? any ideas?

J
John Revere 👤 Member for 11 years 11 months

The resources are not disappearing it's the budget when you click on the actual start of an activity.

J
John Revere 👤 Member for 11 years 11 months

The resource stays it's the budgeted value that changes to zero.

J
John Revere 👤 Member for 11 years 11 months

No it's not being reduced by 8. It automatically disappears or changes to zero when you click on start date. I'm thinking when they setup P6 initially they must of clicked on a box to reset the values to zero. They have assigned resources and wonder if again there is a calculation setting that is causing the disappearance.

J
Jimmy Xie 👤 Member for 12 years 5 months

Dear John

How is your resource "erased"exactly?

Is it erased as 8 times less compare to the original budgeted unit?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts