Cash flow distribution in P6

I need to change the way that P6 distribute the budget cost.Its distribute the cost for each work hour ,for example if I have one activity start on 10 Apr.14 and finish on 10.May.14 the P6 will devide the cost of the activity to two parts , one in april and one in may according to the units ( the work hours ).

but I need to make the P6 respect the start or finish dates.,to put the total cost of the activity in one month .

there is some way ?

R
Raymund de Laza 👤 Member for 16 years 6 months

Yes, absolutely I did not get your point.

In my understanding now, you want the Assignment to be eitheir on the Fist Day or at the End of the activity Duration.

I suggests Make use of the Resource Curve.

O
Osama Haggag 👤 Member for 12 years 3 months

I think taht you didint got my point,what i need is to put all money for same activity in one month not devide according to days,If the activity start on Jan an finish in Feb , I need to assighn all budget cost in Jan,no to make part in Jan and part in Feb

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts