I am new to planning and am trying to understand link logic and am getting very confused. I have only used finish to start links or finish to finish. Can you please tell me why have a start to finish and what does it do different to a finish to start. It seems to be the same thing to me. One task ends before another can start.
Hi Sarah
Using Finish Start links is the correct procedure for the construction industry so please continue with that method.
Other schedulers use Start Start links with a lead lag but this is a lazy approach - I have had many a debate in PP on this topic so maybe another will start up.
There is no place for a Finish Finish link unless you have to close out a SS link creating a "ladder" sequence.
A ladder is fine for a manufacturing but not much use in construction.
There is no point in Start Finish link in any programme although I have seen it used once when a construction director was using them to create an As Late As Possible sequence. When I showed him the ALAP button he changed his ways.
The only place for a FS Lead Lag is to allow for drying out or curing when the time lag must be in calendar days.
Best regards
Mike Testro