Resource Duration Equal to Activity Duration

I created a cost loaded schedule. I did not do anything with the resource durations; when creating the schedule I just entered the duration in the activity duration column. I now need these activity durations to be copied into the resource durations without having to hand key in for all 2500 activities. I do not need the resource durations to change with the units, I just need the resource duration to always correspond with the respective activity duration.

Currently, all resource durations are 0 for non-progressed activities. Activities that have started display the actual activity duration

Let me know if you need any other info that would help out.

E
Eric Preisendanz 👤 Member for 12 years 4 months

My units do not correspond to my duration. I have set up a $1 to 1 unit ratio. So an activity of $5000 would be 5000 units. But the duration is based on the predetermined duration of the activity. I need to transfer all of the activity durations to the resource durations (i.e.: Activity ID AA100: Duration = 5 days. all resources assigned to that activity need a resource duration = 5 days)



Let me know if this is possible

R
rowstone fausto 👤 Member for 15 years

Good day Eric,

 

Just make your default unit/time  equal to 1 for all  assigned resourses. To make your activity duration equal to your budgeted units.

R
Raymund de Laza 👤 Member for 16 years 6 months

Eric,

See if the Resource Calendar is the same as the Activity Calendar and as well as the Default Calendar.

 

Regards,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts