Hi
Running a schedule of 30 projects, circa 50k activities with a large numver of interproject links.
At random times and on random activities I am seeing the resource dates either inside or outside of the activity Start and Finish dates.
Has anyone else experienced/resolved this please?
H.
Helen,
Have to check if the Resource calendar is the same as Activity Calendar and as well as Default Calendar.
Regards,