Resource and activity date misalignments

H
Helen Ward 👤 Member for 13 years 3 months

Hi

Running a schedule of 30 projects, circa 50k activities with a large numver of interproject links.

At random times and on random activities I am seeing the resource dates either inside or outside of the activity Start and Finish dates.

Has anyone else experienced/resolved this please?

H.

R
Raymund de Laza 👤 Member for 16 years 6 months

Helen,

Have to check if the Resource calendar is the same as Activity Calendar and as well as Default Calendar.

 

 