Gannt chart showing logic between baseline activities

J
John Wilson 👤 Member for 15 years 7 months

I am using P6.7 and have copied and pasted with a base line a very simple schedule, which seemed to work ok

When I view the current schedule with baseline and also the logic links the logic is between the baseline activities.

Has anyone seen it before and what was the solution

Rgds John

J
John Wilson 👤 Member for 15 years 7 months

Sorted it

If the baseline bar has higher priority that the remaining bar the logic will go to the baseline activities

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts