I am using P6.7 and have copied and pasted with a base line a very simple schedule, which seemed to work ok
When I view the current schedule with baseline and also the logic links the logic is between the baseline activities.
Has anyone seen it before and what was the solution
Rgds John
Sorted it
If the baseline bar has higher priority that the remaining bar the logic will go to the baseline activities