Actual Cost's Are Not Distributing Correctly

I have a project where the actual costs are not distributed in accordance with the actuial dates for that activity. Instead, the costs are placed on the data date and cause a graph spike. this occurs when the "sort costs by financial period" option is turned off. Does anyone know what causes this? 

R
Raymund de Laza 👤 Member for 16 years 6 months

Brook,

I suggest 2 Things:

1. Try to assign a resource curve on the Resource.

2. Remove and Re-assing the same Resource.

 

Regards,