I have a project where the actual costs are not distributed in accordance with the actuial dates for that activity. Instead, the costs are placed on the data date and cause a graph spike. this occurs when the "sort costs by financial period" option is turned off. Does anyone know what causes this?
Actual Cost's Are Not Distributing Correctly
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Brook,
I suggest 2 Things:
1. Try to assign a resource curve on the Resource.
2. Remove and Re-assing the same Resource.