Working with Sub Projects

 

We have a contractor who is using a sub project built onto our main project schedule.

 

Our data date is a month different from theirs (theirs being a month behind ours). When looking at the critical path and you accept relationships from other projects can there be an issue from having these two different dates?

 

Obvious is that the sub project isnt updated to the newer date but what abpout float and assessing critical paths etc?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Martyn

Instruct your contractor to synchronise his dates with yours.

Best regards

Mike Testro