Resource Levelling

Dear All,

I have Created A programme in p6, resource is also loaded. some of the resources overloaded. i can see that in resourse usage profile. but i tried to level the resource using resource levelling wizard, but its not working. after resource levelling max unit per time should increase to accomodate the overallocated resource, but it not happening in my case. i have been trying to solve this from past two days plz help me.......

R
Ravi Katare 👤 Member for 11 years 10 months

Hi

Check the duration type, It should not be Fixed duration one

 

- Ravi

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Siddiqui

Efficient resource leveling is not easy. If resources are overloaded, then you have not many options. The first one is to allow the end date of the project to move to allow the resources to be leveled. The second option is to increase the number of resources in the resource availability.  There are many options to level the resources but these are not easy and require fundamental knowledge of scheduling. 

I have some articles on resource leveling  for beginning and junior planners on my website that can help you.

www.plannenvoornietplanners.net

Regards Johannes

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts